Dan walks every project through this exact sequence so nothing falls through the cracks.
- Buyer finds the property and makes offer
- Dan is contacted by Loan Officer/Realtor/Client once contract is ratified
- Dan performs initial inspection and prepares work write-up (usually 3–7 days)
- Lender runs numbers and issues conditional approval
- Appraisal is ordered on “as-is” + “as-repaired” value
- Closing occurs – repair funds go into escrow
- Borrower selects contractor(s) and work begins
- Dan performs draw inspections as work progresses
- Final inspection and certification
- Lender releases final draw – homeowner moves in
Common Timeline Realities
- Inspection to work write-up: 3–7 days
- Full approval to closing: 30–45 days
- Renovation duration: 3–12 months depending on scope